BALLARD REPORT ACTIVITIES
WT2.1. A package with data for 3 Backup systems has been shared with the partners from the WP.
WT2.2. The necessary documents (Stack and System manual, test protocol) have been shared with the partners in the WP. Several meetings have been held in the group to align on the details from the Test protocols to be performed for the stack and the systems to be tested.
WT2.3. A mockup has been made at BPSE’s premises from a 5kW system, to be ready for testing by EIFER. The Mockup contains one new stack. The mockup has been delivered to EIFER. The other two stacks will be delivered later in the project, when the testing planning requires them.
WT2.4. The first system has been sent and installed at UBFC. The second system has been installed at BPSE’s facilities. Both systems are ready for testing.
WT4.4. Several meetings have been held together with the partners to analyze the data shared on WT2.1.
WT6.2. The activities for allowing the performance of EIS measurements on-board the BPSE PEMFC are ongoing. Pre-study shows that the DC/DC converters could not be modified for the project scope. Alternative feasibility study has been made to see if we can use the system’s internal booster for same purpose. Multiple meetings have been held with partners for ensuring alignment for technical functioning.